Moving from Foundation, Spectrum or ComputerEase to a new ERP: how to keep your reporting
By the Junction team · Published 18 November 2026 · 6 min read
The short answer
- Foundation, Spectrum and ComputerEase are construction accounting systems that Junction connects, so you can keep asking the old one while you build the new.
- Six questions cross the cutover: open jobs, committed cost, retainage, payroll history, WIP and payables ageing, and each needs a written answer on where it will be read from.
- Everything here is practice advice for your controller to test, not a statement about what any vendor offers for migration.
Most of this guide is practice advice, not fact about any vendor, so test it with your own controller. It assumes you run Foundation, Spectrum or ComputerEase today, you are moving to another system, and people will keep asking questions that need numbers from both.
What do you still need to answer across both systems?
Six questions tend to straddle the cutover for a contractor: open jobs, committed cost, retainage, payroll history, work in progress and payables ageing. For each, decide before cutover whether the old system, the new one, or both will answer it, and who owns the answer.
| Question | Why it straddles the cutover | A decision to make |
|---|---|---|
| Open jobs | A job started in the old system finishes in the new one | Which system holds the job's cost to date at the cutover date? |
| Committed cost | Subcontracts and purchase orders signed before cutover are still being paid after it | Are open commitments loaded, or read from the old system until closed? |
| Retainage | Held and released amounts span both systems for months | Who tracks what is held on each side, and how is a release matched? |
| Payroll history | Year-to-date earnings, burden and union reports mix both | Who may see old payroll, and for how long? |
| WIP | Percent complete needs cost to date, so both sides | Which system produces the first WIP schedule after cutover? |
| Payables ageing | Invoices entered before cutover are paid after | Do unpaid invoices move, or are they paid from the old system? |
The same six questions appear in report across old and new ERP during migration; this guide applies them to these three systems.
What stays behind in the old system, and what does the new system start with?
Frame it as questions for you and your controller, not as rules. For each type of data, decide whether it stays in the old system, starts in the new one, or both. Write the answers on one page and have your auditor and surety contact see it.
| Data | What may stay behind | What the new system may start with | Ask your controller |
|---|---|---|---|
| Closed jobs | Final cost and billing by cost code | Perhaps a summary per job | How many years of job history will the new system need? |
| Open jobs | Detail before the cutover date | Cost to date by cost code, open commitments | Will a job's detail be split across two systems? |
| Payables and receivables | Paid invoices and receipts | Open items only | Is there a unique invoice reference to match across both? |
| Retainage | Settled retainage history | Retainage held at the cutover date | How is a release in the new system linked to the old record? |
| Payroll | Past years of earnings and certified payroll | This year's totals and employee records | Who keeps access to past payroll, and who is excluded? |
| Cost codes | Old structure as it was | A mapped or new structure | Is there a map, and who maintains it? |
For the cost code part, see map cost codes between old and new construction ERP. For the choice of what moves, see what job cost data to migrate and what to leave behind.
What questions matter most for each of the three systems?
Foundation, Spectrum and ComputerEase are construction accounting systems that Junction connects, and the questions that matter are similar. We make no claim about how any of them handles migration. Use these paragraphs as prompts for your own review of the system you run.
[Foundation](/construction/connect/foundation). Ask which jobs will still be open in the old system after cutover and how their committed cost is tracked. Ask who currently reads job cost and payroll reports, and which of them need old data after the move.
[Spectrum](/construction/connect/spectrum). Ask how retainage and change orders on open jobs will be carried, and which reports your owners and surety use that rely on history. Decide if you will need old data for the same job in two places.
[ComputerEase](/construction/connect/computerease). Ask which reports your team runs weekly and monthly, and which of them reach back more than one year. Those are the ones that break first at cutover, so list them with an owner before the date is fixed.
How do you keep the old data reachable and permissioned?
Keep the old system available, backed up and restricted to the few people who need it, then give each of them access only to the jobs and fields their role requires. That is our advice. The aim is reach without a free-for-all, particularly over payroll and bonding history.
- Name an owner for the old system's data and for the day it is switched off.
- Fewer logins. Most staff need the new system. Keep old access for the controller, payroll and a deputy.
- Limit by job and field. An estimator may need cost by job but not pay rates. Set that before the cutover, not after.
- Keep an audit trail of who asked what. Names and outcomes are enough.
- Back up at cutover and test a restore once. Store it away from the working copy.
More options for keeping the old data reachable are in keep access to legacy construction data.
How do you ask both systems at once?
Connect the old system and the new one to one connector, add it to Claude, ChatGPT, Gemini or Copilot, and ask in plain language. The connector reads each system when you ask, applies each person's roles, and the answer says which system each figure came from.
Questions for a Foundation, Spectrum or ComputerEase move
- For every job open at the cutover date, show cost to date in the old system and cost since cutover in the new one, with one total per job.
- List subcontracts and purchase orders signed before cutover that still have a balance, and show which system holds each.
- Show retainage held by job in the old system at cutover and the same jobs in the new system today.
- Which unpaid vendor invoices in the old system are more than 60 days old?
Before you start, use the cutover checklist for controllers to confirm the checks that must pass.
Frequently asked questions
- How do I keep reports after moving from Foundation software to a new ERP?
- Decide which system answers each question across the cutover, keep the old system available and permissioned, and ask both through a connector that reads each when you ask. This is practice advice, not a vendor claim.
- How do I report on Spectrum ERP history after migration?
- Keep the old Spectrum data reachable and decide a cutover rule, such as reading old history up to a date and the new system after it. A connector that reads both lets you ask one question across the date.
- What happens to my ComputerEase data when I migrate?
- That depends on what you load and what you leave behind, which is your decision with your controller. Whatever stays behind needs a plan for who can reach it and for how long.
- Which reports break first when you change construction ERP?
- Usually the ones that reach back over a cutover: WIP, retainage, committed cost on open jobs and payables ageing. List them, with an owner, before the date is fixed.
- Can I ask the old and new system one question at the same time?
- Yes, if both are connected to one MCP connector. The assistant reads each system when you ask, within each person's permissions, and shows where each figure came from.